ISLAMABAD — Prime Minister Shehbaz Sharif has taken notice of repeated procurement delays involving nearly Rs 928 million worth of sports equipment for the 2027 South Asian Games. The board has struggled to award contracts for sound systems, timing devices, and generators despite multiple failed bidding attempts.
Pakistan Sports Board Director General Yawar Hussain stated that the board made six attempts to award the projects through government-to-government arrangements. He noted that the board has now obtained approval to initiate a fresh bidding process to resolve the ongoing procurement impasse.
The board initially launched open competitive bidding in March 2025, awarding only Rs 591.334 million for electronic scoreboards. A July 2026 government-to-government exercise was cancelled after the Pakistan Engineering Council clarified that the sole bidder was not independently licensed as a contractor.
In September 2026, the board advertised a fresh open bidding process but cancelled it on October 17 without opening bids on the Electronic Public Procurement and Disposal System. A subsequent Letter of Intent for Rs 927.758 million was issued on October 27 but cancelled in early November following intervention by higher authorities.
The cancellation of the Rs 927.758 million contract, which covered electronic timing devices, sound systems, and diesel generators, highlights significant logistical challenges. With the games scheduled for April 2027, the board faces a compressed timeline to secure compliant contractors and finalize critical infrastructure procurement.