KARACHI / ISLAMABAD — The Asian Development Bank has granted a conditional extension for its financing loan supporting Karachi’s delayed Bus Rapid Transit Red Line project, tying continued support to strict performance benchmarks set for April 2027. According to project officials, international lenders raised serious concerns regarding sluggish construction progress, prompting a revised agreement that mandates specific target completions within a strict timeframe.
TransKarachi, the designated implementing agency for the urban transport undertaking, reported that most compliance requirements have already been fulfilled, with remaining milestones expected to be met ahead of schedule. A primary focus involves finalizing new contracting arrangements for the 12.8-kilometer Numaish-to-Mosamiyat segment, designated as Lot 2, after previous agreements were terminated in April due to persistent operational delays.
Additional core benchmarks entail constructing an underground bus staging facility adjacent to Numaish capable of housing approximately 100 dedicated transport vehicles, alongside relocating the airside perimeter fence managed by the Pakistan Airports Authority. Originally initiated in March 2022, the mass transit venture has encountered continuous setbacks that have escalated total projected expenditures to $725 million.
Project authorities have established a revised overarching completion goal of June 2028. Meanwhile, phased timelines indicate that the primary corridor under Lot 1 should reach completion by December 2026, followed by the Malir Halt segment in April 2027 and the Bagh-i-Karachi section by July 2027.